Because of a lapse in government funding, the information on this website may not be up to date, transactions submitted via the website may not be processed, and the agency may not be able to respond to inquiries until appropriations are enacted. The NIH Clinical Center (the research hospital of NIH) is open. For more details about its operating status, please visit cc.nih.gov. Updates regarding government operating status and resumption of normal operations can be found at opm.gov.

ORF Home > Project Resources > Project Tools > Checklist for Reviewing Project Plans

Checklist for Reviewing Project Plans

back

Scientists often don’t have experience in reviewing plans for their space, so they don’t always know what to look for on the drawings. NHGRI developed the following list of items to help its scientists know what to look for and what questions to ask.

Cooling
  • Location of air cool units in relation to furniture
  • Cooling for electronics in conference rooms
  • Cooling adequate for copiers
  • Cooling adequate for other equipment
Doors
  • Door glass for inner doors
  • Door glass for outer doors; fireproof rating
  • Door closures, yes or no
  • Door size for equipment clearance
Electronics
  • LAN connections in relation to furniture
  • Conference room connections
  • Types and locations of electronics’ connections in conference room
  • Electrical and LAN for Airports in ceiling
  • Videoconferencing capabilities; analog and ISDN lines
Equipment
  • Equipment placement
  • What’s over the equipment in the ceilings?
Miscellaneous
  • Asbestos
  • Placement of columns
  • Drains
  • Signage
Power and Lighting
  • Emergency power
  • Electrical outlets
  • Amount of lighting
  • Types of lighting in general
  • Types of lighting in conference rooms
  • Dimmers in conference areas
Storage
  • Storage of conference chairs and tables
  • Supply storage space